Flooring Removal Sioux Lookout Ontario
This removal was a great challenge!
This floor was very old and some areas had wood subfloor that was disintegrating when we touched it.
This work also had to be done after hours and under a very tight timeline as the retail location wanted to be open for business within 2 days of our start.
In order to keep to the schedule and give the flooring contractor the maximum amount of time, we started at closing time on Friday and worked through the night so that the flooring contractor could start first thing the next morning and have 2 full days to complete the work.